In Round Rock a kitchen and a bathroom remodelled as one project go on one permit, not two. The City of Round Rock states that it operates under a combined one-permit system, which means that any associated electrical, plumbing or mechanical work must be included in the same permit. That single rule is what makes combining the two rooms a different job from running them a year apart, and it changes the paperwork, the trade sequence and what you live through in the middle.
One application, one set of plans, one review clock
Combining the rooms collapses three separate processes into one. The City's single-family remodel page asks for one complete set of construction plans, which must include any structural, mechanical, electrical and or plumbing changes, so both rooms are drawn together rather than as two submissions. Plan review then typically takes 30 business days from the date the application is received and accepted, and the City is explicit that expedited reviews are not available.
That 30-business-day clock runs once per application. Two rooms submitted together go through it once; the same two rooms submitted months apart go through it twice. This is the strongest practical argument for combining, and it is a scheduling argument rather than a cost one.
The flip side is that one permit means one approval. If the bathroom drawings raise a review comment, the kitchen waits with it, because the City issues the permit only once all review comments have been addressed and all required reviews have been completed and approved. Bundling a simple room with a complicated one ties the simple room to the complicated one's timeline.
Every trade on both rooms has to be on the application
The permit does not issue until the people doing the work have confirmed they are doing it. Round Rock's rule is that the general contractor and all applicable MEP subcontractors have to confirm their assignments through their own Permit Portal accounts before issuance. Subcontractors must accept their assignment in the portal to be included in a permit, and although that confirmation is not mandatory when the application is submitted, it is required before the permit is issued.
With two rooms that usually means more trades, not the same trades twice. All contractors and subcontractors applying for a building permit in Round Rock must be registered, and the City charges no registration fee and no annual fee, so there is no reason for a legitimate trade not to be registered. Ask your contractor to confirm that every plumber and electrician on both rooms is registered and has accepted the assignment, because a single trade that has not clicked accept holds the whole permit.
Texas itself does not license general contractors. As the City of Austin puts it on its contractor registration page, anyone can be a general contractor in Texas, including homeowners, and a state licence is not required. The licensing that exists is on the trades: the Texas Department of Licensing and Regulation states that anyone who performs or offers to perform non-exempt electrical work in Texas must be licensed, and the Texas State Board of Plumbing Examiners licenses plumbers and publishes a public licence search. Look both up yourself.
Which trades overlap, and why that is the real reason to combine
A kitchen and a bathroom draw on the same trades in the same order, which is why running them once is less disruptive than running them twice. Both rooms need a plumber for rough-in, an electrician for circuits and lighting, a tile setter for floors and wet walls, and a finish carpenter for cabinetry and a vanity. Doing them together means each of those people comes to your house once, works through both rooms, and leaves.
That overlap is also why the plans have to be drawn together. Our kitchen remodeling and bathroom scopes both cover tile, fixtures, lighting and ventilation, and the sequence between the two rooms has to be decided before anyone starts, not negotiated while a plumber is standing in the hall.
If either room involves taking out a wall, that is its own step: Round Rock requires an engineered design for structural modifications such as wall removal. An older house adds two more. The City strongly recommends an asbestos survey if walls are to be removed from a home built before 1980, and the EPA requires that anyone paid to perform work disturbing paint in housing built before 1978 be certified.
What you actually live through
The honest cost of combining is that you lose a kitchen and a bathroom at the same time. That is a real household problem and it is the question most worth settling before anyone signs anything. Work out which bathroom stays usable for the duration, where a temporary kitchen goes and what it needs, and whether anyone in the house cannot manage stairs to reach the remaining bathroom.
Inspection timing shapes the middle of the job too. Round Rock takes inspection requests by 4:00 p.m. for the next business day, and the City notes that next-business-day inspections are subject to availability and are not guaranteed. Inspections run Monday through Friday between 8:00 a.m. and 3:00 p.m. Two inspections of each type are included in the permit fee, and after two failed inspections of the same type a re-inspection fee applies to each additional one, so getting work right the first time matters to the schedule as well as to the bill.
The City publishes a residential inspection list but says it serves as a guide only and that inspections may vary depending on the scope of work, which is another reason the two rooms are planned as one scope rather than two. Round Rock's adopted codes include the 2024 International Residential Code, the 2024 International Building Code, the 2024 International Energy Conservation Code, the 2024 International Mechanical Code, the 2024 International Plumbing Code and the 2023 National Electrical Code, and a contractor who works across Central Texas has to know which edition applies where.
What to settle before the first visit
- Which bathroom stays usable, and where the temporary kitchen goes
- Whether either room involves removing a wall, which brings an engineered design
- The year the house was built, for the pre-1980 asbestos survey and the pre-1978 lead rule
- Whether the property carries Historic Overlay Zoning, which needs a Certificate of Appropriateness before a permit issues
- That every trade on both rooms is registered with the City and will accept the assignment in the portal
- The sequence between the rooms, written into the scope rather than decided on site
Anything you are unsure of, the Building Inspection Division answers directly on 512-218-5550, Monday through Friday from 7:00 am to 4:00 pm, at 301 W Bagdad Ave Suite 100 in Round Rock.
Who to hand it to
Both rooms on one permit asks more of the contractor than either room alone, because one set of plans has to carry both scopes and every trade on both has to be registered, added and confirmed before anything is issued. The useful question on a first call is not how fast someone can start. It is whether they have run a combined Round Rock permit before and can say what the sequence between the two rooms will be.
We are veteran-owned and BBB accredited, and neither is the reason to hire us. The part you can test before signing is that we return calls within two hours during business hours, we document every project with photos start to finish, and there are no surprise costs. Round Rock is in our service area along with Austin, Cedar Park, Pflugerville, Buda and Kyle. Call 737-235-2776 or book a consultation and tell us which two rooms you are planning.